Solar Farm Online

2020-04-27T05:32:32+00:00November 1st, 2020|

Upon completion of testing and startup, the solar farm will begin delivering power to the community, offsetting 25% of the

Testing and Startup

2020-04-27T05:32:32+00:00September 20th, 2020|

Once all of the infrastructure is in place, wiring of the solar farm can occur.

Installation

2020-05-05T16:21:52+00:00April 3rd, 2020|

Construction will consist of putting screw piles in the ground and erecting the frames and racking that the solar panels

Material Shipment

2020-05-05T16:20:21+00:00February 20th, 2020|

With the increase in the load limit for winter road, materials for the 3NE solar farm are shipped into the

Site Clearing

2020-05-05T16:19:57+00:00February 7th, 2020|

Site clearing for phase 2 begins, which involves removing trees and small shrubs.

3NE Receives Regulatory Approval

2020-05-05T16:19:05+00:00January 15th, 2020|

3NE receives regulatory approvals from the Alberta Utilities Commission (AUC) to construct and operate phase 2 of the solar farm.

NRCAN News Release

2020-05-28T22:45:36+00:00August 27th, 2019|

Phase I is complete 400 kW phase I solar project is operational and producing power with enough power for 75

Phase 1 solar

2020-10-07T23:31:07+00:00August 20th, 2019|

The 600 kW Phase I solar project is operational and producing enough power for 75 homes.

Community Celebration Event

2022-10-17T17:05:07+00:00February 7th, 2019|

Community holds an event to celebrate the launch of the joint project. Official signing between Athabasca Chipewyan First Nation (ACFN),