Solar Farm Online
Upon completion of testing and startup, the solar farm began delivering power to the community, offsetting 25% of the community’s
Upon completion of testing and startup, the solar farm began delivering power to the community, offsetting 25% of the community’s
With all of the infrastructure in place, wiring of the solar farm took place.
Workers are back onsite at the 3NE solar farm site near the airport in Fort Chipewyan – continuing the work
Construction consisted of putting screw piles in the ground and erecting the frames and racking that the solar panels would
Land clearing has begun for the solar farm Land clearing has started on the second phase of Canada’s largest off
February 20th marked the arrival of “The Growcer” — an indoor hydroponic farm that is contained within a portable seacan.
February 20, 2020) With the increase in the load limit for the winter road, materials for The Three Nations Energy
With the increase in the load limit for winter road, materials for the 3NE solar farm were shipped into the
Site clearing for phase 2 begins, which involves removing trees and small shrubs.
The Alberta Utilities Commission (AUC), the regulatory body associated with power generation in Alberta, approved the application from 3NE to