solar farm aerial
The 3NE owned phase 2 solar project adds 2,200 kW of solar to the project.
The Fort Chipewyan solar farm (phases 1 & 2) from the air.

It’s a thing of beauty! Construction is almost complete on the 2,200 kW Three Nations Energy (3NE) solar farm. Phase 2 is in addition to the 600 kW installed in the ATCO project in August of 2019. Delta Construction is installing the perimeter fencing on the property and Clark Builders and ATCO are finalizing construction and the wiring.

The next stage is to move into testing of all the equipment. 

Also on site is the new firewood processor. This machine arrived in the community on July 19th and is continuing to be used to process the salvage wood from the site into cordwood.